PWSA Ongoing Water Main Work On Lothrop, Terrace, & Darragh Sts Thru Nov 2016


Warning: Undefined variable $output in /home2/oakcliff/public_html/wp-content/themes/mw-small-Oakcliffe/functions.php on line 103

pdf icon PWSA-Lothrop-Terrace-Darragh-Streets.pdf

  • Construction commenced on June 13, 2016.
  • Installation of main waterline on Lothrop Street is 50% complete from 5th Avenue to Victoria Street.
  • Concrete paving base restoration is being completed as each 100-foot section of main waterline is installed.
  • The project is approximately 10% complete.
  • The anticipated project completion date is November 2016, weather permitting.
Check the attached flyer for map and more info.